Founder Motor (Deqing) Co., Ltd. has entrusted our institute to compile the Environmental Impact Report for the Project of Annual Production of 2.2 Million Sets of New‑Energy Intelligent Drive Systems of Founder Motor (Deqing) Co., Ltd. In accordance with the relevant provisions of the Environmental Impact Assessment Law and the Measures for Public Participation in Environmental Impact Assessment, we hereby conduct an environmental public notice to solicit public opinions. Details of the notice are as follows:

I. Name and Overview of the Construction Project

Project Name: Project of Annual Production of 2.2 Million Sets of New‑Energy Intelligent Drive Systems.

Developer: Founder Motor (Deqing) Co., Ltd.

Project Nature: Expansion

Project Location: Plot east of Fazhan Avenue and south of Fenghuang Road, Shacun Block, Chengbei High‑tech Park, Huzhou Moganshan High‑tech Zone (within the existing factory premises)

Project Content: The enterprise intends to utilize idle areas in Workshop No.1 and idle land within the factory site to construct new production workshops. Equipment including stator and rotor production lines will be procured for implementing the project with an annual capacity of 2.2 million sets of new‑energy intelligent drive systems. The total project investment amounts to RMB 1,696.76 million, and the expected sales revenue upon full operation will reach RMB 580 million.

II. Name and Contact Information of the Project Developer

Developer: Founder Motor (Deqing) Co., Ltd.

III. Name and Contact Information of the EIA Institution

EIA Institution: Huzhou Baoli Environmental Technology Co., Ltd.

Address: 15th Floor, Deqing Chamber of Commerce Building

Contact Person: Mr. Song, Tel.: 18657226775, Postal Code: 313299

IV. Web Link for Public Comment Form

Please refer to the link attached to this announcement for the public comment form.

V. Methods and Channels for Submitting Public Comment Forms

The public comment form mainly collects suggestions and opinions concerning environmental impacts and environmental protection measures of this project.

Submission methods: Phone call, fax, email, mail and other means are acceptable.

Submission channels: 1. Contact the EIA institution; 2. Contact the project developer.

VI. Miscellaneous

During the preparation of the draft environmental impact report for comments, the public may submit opinions related to environmental impact assessment to the project developer.

EIA Institution: Huzhou Baoli Environmental Technology Co., Ltd.